Company Completed the Repair of Turbine of Unit №2 Zuevskaya TPP

August 29, 2017

Completed overhaul of the steam turbine K-300-240-2 (HTGZ) # 2 of Zuevskaya TPP. The work took place from 04.06.16 on 12.09.16.

The project involved the dismantling of all the cylinders: high pressure cylinder, cylinder of medium pressure and low-pressure cylinder. In addition, steam distribution and control systems were repaired. The first and second supports translated into metallfluoroplastict.